West 11th Avenue (from Waterloo Street to Blenheim Street) sewer construction project
City crews to upgrade the sewer main along West 11th Avenue.
Project details
Location
- 3300 blk West 11th Avenue (from Waterloo Street to Blenheim Street)
Expected duration
- Start: Monday, September 23, 2013
- End: Friday, October 18, 2013
Hours of work
- Monday to Friday, 7:00am to 3:30pm (may include weekend work)
Status
- Completed
Impacts to traffic, parking and residents
Traffic on West 11th Avenue will be closed off or reduced during construction. Traffic delays will be expected.
Residents access will be maintained at all times.
Local parking may be affected by the presence of work trailers and construction equipment.
How this project will improve the city
This project will improve the condition of the current sewer main in this neighbourhood.