Skeena Street utility construction project

Fortis BC crews are working at a section of Skeena Street for utility construction work.

Location

  • 0-300 blk Skeena St (from Dundas St to East Hastings St)

Expected duration

  • Start: Thursday, June 20, 2013
  • End: Friday, July 5, 2013

Hours of work

  • Monday through Friday, 7:00am to 5:00pm

Status

  • Completed

Impacts to traffic, parking, businesses and residents

Traffic on Skeena Street will not be closed during construction, though traffic delays can be expected.

Street parking may be affected by the presence of work trailers and equipment.

Temporary No Stopping signs will be installed on both sides of Skeena St from the lane north of Dundas St to 500 meters south. Temporary parking restrictions will be removed as soon they no longer needed.

Access to businesses and residents will be maintained.

 

 

Applicant contact

Fortis BC contact
Nick Ong
Phone: 604-592-7910

City contact

Utilities Management Branch
Phone:
604-873-7000