Home > Streets and transportation > Driving and traffic > Road closures and construction > Kootenay Street sewer reconstruction project

Kootenay Street sewer reconstruction project

City crews are working to upgrade the sewer system along Kootenay Street.

Location

  • 0 blk Kootenay Street (from Triumph Street to Dundas Street)

Expected duration

  • Start: Monday, July 08, 2013
  • End: Friday, July 26, 2013

Hours of work

  • Monday┬áto Friday, 7:00am to 3:30pm

Status

  • Completed

Impacts to traffic, parking and residents

Kootenay Street from Triumph St to Dundas St will be closed to all traffic during construction.

Residents access will be maintained at all times.

Street parking may be affected by the presence of work trailers and construction equipment.

How this project will improve the city

This project will improve the condition of the current sewer system in this neighbourhood.

City contact

Project Coordinator
Simone Rousseau

Phone: 604-873-7375
simone.rousseau@vancouver.ca