Knight Street Water and Sewer Upgrades

Upgrades complete

We have replaced the water main, installed a separated sewer main, and repaved the road surface on Knight Street between 13th and 37th avenues.

Work took place between 13th and 37th avenues, with other work on some connecting side streets.

This project will improve water and sewer main infrastructure in the area. The new pipes are expected to serve the neighbourhood for 100 years.

Project details

Location:

  • Knight Street, E 13th to 37th avenues

Project duration:

  • Start: November 2016
  • Completed: July 2017

Hours of work:

  • Monday to Friday: 7:00am to 3:30pm
  • Weekends as needed
Section Estimated start Estimated end
13th to 15th Ave November 2016 July 2017
King Edward to 32nd Ave January 2017 July 2017
15th Ave to Kingsway January 2017 June 2017
Knight and 15th Ave intersection March 2017 June 2017

How this project may affect you

Construction will occur on Knight Street and will occasionally impact adjacent streets. Each block may be impacted by construction for several months. The construction work is being carefully planned to limit the overall impact to residents, businesses, and road users. During construction, one travel lane in each direction will stay open on Knight Street.

Traffic

All lanes are fully reopened to traffic.

Parking

Parking will be restricted to accommodate construction. Restrictions will change during the project and will be removed as soon as they aren't needed.

Access to residences and businesses

Access to residences and businesses will be maintained at all times.

Sidewalks and crosswalks will generally be maintained during construction or alternate facilities will be provided.

November 2016 to April 2017

  • Access to homes on 15th Avenue is from adjacent streets
  • The north crosswalk at Knight Street and 15th Avenue is closed

Water supply

We will provide advanced notice of any disruption to your water supply, except if there is an emergency. During construction, you may occasional notice cloudy water. This cloudiness is not a health concern and will usually go away within a few hours.

Get help with water quality and water pressure problems