Home > Streets and transportation > Driving and traffic > Road closures and construction > Fir Street sewer reconstruction project

Fir Street sewer reconstruction project

City crews are working to upgrade the sewer main line along Fir Street.

Location

  • 2000 blk Fir St (from W 4th Ave to W 5th Ave)

Expected duration

  • Start: Monday, May 13, 2013
  • End: Friday, June 14, 2013

Hours of work

  • Monday through Friday, 7:00am to 3:30pm

Status

  • Completed

Impacts to Traffic, parking and businesses

Traffic on Fir Street will not be closed during the construction, though traffic delays can be expected. One lane on each direction will be maintained for traffic.

Access to businesses will be maintained at all times.

Local parking may be affected by the presence of work trailers and equipment. Temporary parking restrictions will be removed as soon they no longer needed.

How this project will improve the city

This project will improve the condition of the current sewer system on this neighbourhood.

 

 

 

City Contact

Project Manager
Keith Der
Sewers Design Branch

Phone: 604-871-6430