East 20th Avenue (lane south) sewer reconstruction project

City crews will be working to upgrade the sewer main line on the lane south of East 20th Avenue.

Location

  • Lane south of 100 East 20th Avenue (from lane west of Main St to Quebec St)

Expected duration

  • Start: Wednesday, June 19, 2013
  • End:  Tuesday, July 02, 2013

Hours of work

  • Monday through Friday, 7:00am to 3:30pm

Status

  • Completed 

Impacts to traffic, parking, businesses, residents

East 20th Avenue will have partial road closures during construction and traffic delays can be expected.

Residents access will be maintained at all times.

Street parking may be affected by the presence of work trailers and equipment. Temporary parking restrictions will be removed as soon they no longer needed.

How this project will improve the city

This project will improve the condition of the current sewer main line on this neighbourhood.

City contact

Project Coordinator
Natalie Tokgoz

Phone: 604-673-8101
natalie.tokgoz@vancouver.ca