Home > Streets and transportation > Driving and traffic > Road closures and construction > Davie Street sewer main construction project

Davie Street sewer main construction project

City crews have begun the construction of the sewer main along Davie Street from lane east of Howe Street to lane east of Hornby Street.

Project details

Location

  • 700 - 800 blk Davie Street (from lane east of Howe Street to lane east of Hornby Street)

Expected duration

  • Start: Tuesday, February 11, 2014
  • End: Friday, February 28, 2014

Hours of work

  • Monday to Friday, 7:00am to 5:00pm (may include weekend work)

Status

  • Completed 

Impacts to traffic, parking, businesses

During construction, one lane in each direction on Davie Street will be maintained and traffic delays will be expected.  Motorists are advised to plan alternate routes.

Local parking may be affected by the presence of work trailers and construction equipment. Temporary parking restrictions will be removed as soon as they no longer needed.

How this project will improve the city

This project will improve the condition of the sewer system in this neighbourhood.

  

 

City Contact

Project Manager
Keith Der
Sewers Design Branch

Phone: 604-871-6430
keith.der@vancouver.ca