Blenheim Street sewer construction project

City crews are working to upgrade the sewer system along Blenheim Street.

Location

  • 2600-3100 blk Blenheim Street (from West 12th Avenue to West 16th Avenue)

Expected duration

  • Start: Tuesday, August 6, 2013
  • End: Friday, August 16, 2013

Hours of work

  • Monday to Friday, 7:00am to 3:30pm

Status

  • Completed¬†

Impacts to traffic, parking and residents

Blenheim Street will have partial road closures during construction. Traffic delays can be expected.

Residents access will be maintained at all times.

Street parking may be affected by the presence of work trailers and construction equipment.

How this project will improve the city

This project will improve the condition of the current sewer system in this neighbourhood.

City contact

Project Manager
Andrew Ling

Phone: 604-871-6314